6 men can complete a job in 15 days. How many men should work, if the job is to be
completed in 10 days?
Answers
Answered by
1
Answer:
15 days is taken to complete the work by=6 men
1 day will be take to complete the work by=6/15 men
then,
the no of men complete it in 10 days =6/15*10
=4men answer
plz mark the answer brainlist