Math, asked by vinaymy1995, 3 months ago

6 men can complete a project in 25 days and 25 women can complete the same
project in X days. 15 men start working and after 5 days they were replaced by 10
women. If the whole project was completed in 15days, what is the value of, X' ?
1) 10
O 10
46
51​

Answers

Answered by khandelwalmadhav054
0

Answer:

Step-by-step explanation:

10

Answered by amitnrw
0

Given : 6 men can complete a project in 25 days and 25 women can complete the same project in X days.  

15 men start working and after 5 days they were replaced by 10

women.  whole project was completed in 15days

To Find :  value of, X'

Solution:

6 men can complete a project in 25 days

A Man work in a day = M

=> Total Project  = 6 * 25 * M   = 150 M

25 women can complete the same project in X days

A woman in 1 day  = W

=> Total Project = 25WX  

25WX    = 150 M

=> WX  = 6M

Total work done   15M * 5  +  10W*10

= 75M + 100W

75M + 100W  = 150 M

=>  100W  = 75M

=> 4W  = 3M

=> 8W  = 6M

WX  = 6M

=> WX = 8W

=>  X = 8

Learn More:

with P starting the work, working on alternate days P and Q can

brainly.in/question/12303996

With p starting the work, working on alternate days, p and q can ...

brainly.in/question/12364364

Similar questions