6 men can complete electric fiting in a building in 7 days.how many days will it take 21 men to do the job.
Answers
Answered by
2
6 x 7 =21 x a
a=42/21
a=2 days
a=42/21
a=2 days
yash563:
ma
Answered by
5
This question is of Direct and inverse proportions
The following question is specifically of inverse proportion because
as the number of men decrease , the time taken to finish the work increases .
Let's proceed to the method
Let x be the men required
y be the days taken
Men. 6 21
Days 7. y2
Therefore,
x1y1 = x2y2
y2 = 2
Thus,
2 days will be required by the men to finish work in 21 days
The following question is specifically of inverse proportion because
as the number of men decrease , the time taken to finish the work increases .
Let's proceed to the method
Let x be the men required
y be the days taken
Men. 6 21
Days 7. y2
Therefore,
x1y1 = x2y2
y2 = 2
Thus,
2 days will be required by the men to finish work in 21 days