6 men can complete the electric fitting in a building in 7days. How many days will it take 21 men to do the job?
Answers
Answered by
1
Step-by-step explanation:
2men can complete the job in = 7 days 1 man can complete the job in = 6 × 7 = 42 days
∴ 21 men can complete the job in = 42/21 = 2 answer
plz mark me as brainliest answer
Answered by
2
Answer:
2 days.
Step-by-Step Explanation:
→ 6 men can complete the electric fitting in a building in 7 days. So,
→ 21 men can do the job in days. So,
We get,
If the number of men will increase, So, the number of days for the job will decrease. Hence, here is inverse proportion.
Since in inversely proportional term, where x and y has two variations,
Where, k is a constant term.
Here,
x :-
y :-
Therefore,
Hence, 21 men can do that job in 2 days.