6 men can complete the electric fitting in a building in 7 days how many days will it take 21 men to do the job

Answers

Answered by maria9
15
hello friend

6 men can complete the job in 7 days

1 man can complete the job in 6x7 = 42days

21 men can complete the job in 42/21 days = 2 day

hope it helps :-)

amber3: 7×6=42
amber3: use brain
Answered by Anant02
6
let days = x
6 \times 7 = x \times 21 \\ x =  \frac{6 \times 7}{21}  \\ x = 42 \div 21 \\ x = 2 \: days