6 men can complete the electric fitting in a building in 7 days. How many days will it take 21 men to do the job?
Answers
Answered by
24
Answer:
Number of days required by 6 men to complete the work = 7
Number of days required by 1 man to complete the work = 7 × 6
Number of days required by 21 men to complete the work = 42/21 = 2
Hence, 2 days is required by 21 men to complete the work
Answered by
2
Answer:
6 men complete work = 7 days
1 men can complete work = 7×6 = 42
Similarly 21 men can complete work = 42/21 = 2
So,21 men can complete work is 2 days
Similar questions