6 men can do a piece of work in 12 days how many me are needed to do work in 18 days.​

Answers

Answered by adityarajput66
5

Answer:

number \: of \: men \:  = 6

time \: taken \: to \: complete \: the \: work = 12day

work \: to \: be \:done \: in \: 18days

men \: required \: to \: complet \: work \: in \: 18days =

[/tex]</p><p>[tex] \frac{number \: of \: men \:  \times number \: of \: days}{number \: of \: days \: needed}

 =  \frac{6 \times 12}{18}

 =  \frac{72}{18}

4men

So 4 men required