Math, asked by panasmittal, 11 months ago

6 men can do a piece of work in 12 days. how many men would be needed to complete the same work in 6 days?​

Answers

Answered by abhisheksr259
0

Answer:

12 men

Step-by-step explanation:

P1D1=P2D2

6*12 =6*P2

72=6P2

P2=12

therefore 12 men is required to complete the same work