6 men can do a piece of work in 12 days. how many men would be needed to complete the same work in 6 days?
Answers
Answered by
0
Answer:
12 men
Step-by-step explanation:
P1D1=P2D2
6*12 =6*P2
72=6P2
P2=12
therefore 12 men is required to complete the same work