6 men can do a piece of work in 5 days in how many days will 10 men do it
Answers
Answered by
1
total 2-12 days will be there for 10 minutes
Answered by
18
6 men can do work in days = 5 days
1 man can do work in days = 5/6 days
10 men can do work in days = 5/6*10
= 8.3 days
hope it's helpful to you