6 men can do piece of work in 12 days. How many men are needed to do the same work in 18 days?
Answers
Answered by
1
Answer:
12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days.
Step-by-step explanation:
hope this helps you buddy
Answered by
0
Answer:
4
Step-by-step explanation:
6 men can do 1/12 work in one day
x men can do 1/18 work in one day
6------1/12
x-----1/18
Cross multiplying
(6*1/18)/(1/12)=6*12/18=4
Hope it helps
Please mark as brainliest