Math, asked by ashok6123, 11 months ago

6 men can paint building in 5 days .if ten men are employed ,find the number of days in which buildig can be painted​

Answers

Answered by janvitha
14

Answer:

3 days

Step-by-step explanation:

for 6 men it will take 5 days

for 10 men suppose take x days

we have to find x

Men₁ * Time₁ = Men₂ * Time₂

6 * 5=10 * x

x = 6*5/10 =3 days

Similar questions