6 men can perform a job in 15 days how many days will be required for 18 men to perform the job
Answers
Answered by
0
No of days for 1 men = 15/6
=2.5
Therefore no of days for 18 men = 18 x 2.5
= 45
SO 45 DAYS ARE REQUIRED FOR 18 MEN TO PERFORM THE JOB