6 men con complete the electrical flitting in a building in 7 days .how many days will it take 21 men to do the job
Answers
Answered by
1
Answer:x=2
Step-by-step explanation:
6men. 7days
21men. X
Multiply
6×7=21x
X=42÷21=2