6 men do the work in 8 days how many mens are required to finish the work in one day
Answers
Answered by
1
Answer:
42 men are required to finish the work in 1 day
Step-by-step explanation:
Given that 6 men do the work in 8 days
Total work
Now, we have only 1 day
Let number of men required to finish work in 1 day be
Work
Both work should be same, thus we get
Thus, 42 men are required to finish the work in 1 day