6 men finished construction in 30 days. It required to construct the house by 9 men is?
Answers
Answered by
0
Dear,you need the men number or number of days? Make it clear ..
Answered by
0
Answer:
20
Step-by-step explanation:
6/x=1/30
x=30×6
x=180
x stands for no.of days taken by one man
9 men = 180/9=20 days