6 men Or 10 boys can do a piece of work in 15 days. In how many days can 12 men and
5 boys do that work?
pls give ans it's important
aashka5:
answer plsss
Answers
Answered by
4
Answer:
6 men=10 boys
1 man =10/6boys
12 men=10×12/6 boys=20 boys
so,12 men and 5 boys
=20 boys+5boys
=25boys
10 boys can do a work in 15 days
1 boy can do the work in 15×10 days
25 boys can do the work in 15×10/25 days
=6days
so 12 men and 5 boys can do the work in 6 days
Answered by
1
Answer:
the answer will be 6 days