6 Men take 12 hours to weed a certain field. how long would 9 men take to do so if all work at the same rate​

Answers

Answered by ghoshritabratacr7
13

Answer:

12 x 6 / 9 = 8 (Answer)

Step-by-step explanation:

6 men take 12 hrs

Therefore, I men take (12 x 6) hrs

So, 9 men take (12 x 6) / 9

                        = 72 / 9

                        = 8