6 people can do a peice of work in 8days how long will it take 12 people to this peaice of work
Answers
Step-by-step explanation:
______________________________________
6 people can do piece of work in 8 days
So 12 people can do in ____ days?
______________________________________
Here,in this case,
Number of people is inversely proportional to number of days.
As number of people increase days will decrease.
you can easily visualise this..
If number of people is doubled
then,
number of days will be half
So 12 people can do the same work in 8/2 days
i. e 4 days..
AnswEr :
- 6 People work in 8 Days
- 12 People will do that work in how many days?
M₁ = 6, D₁ = 8 and, M₂ = 12, D₂ = ?
• using the Formula Now :
⇒ M₁D₁ = M₂D₂
- Plugging the Values Now
⇒ 6 × 8 = 12 × D₂
⇒ ( 6 × 8 ) /12 = D₂
⇒ ( 1 × 8 ) /2 = D₂
⇒ D₂ = 4 Days.
∴ 12 People will finish the work in 4 Days.
_________________________________
• Shortcut Trick :
In first Part of Question 6 People are Doing work in 8 Days. Then in Second Part of Question People are Doubled so, Days will be half.
↦ 6 People = 8 Days
Doubling the People Means Half of Days.
↦ 12 People = 4 Days
∴ 12 People will finish the work in 4 Days.