6 persons can complete a piece of work in 35 days.
(a) How many persons are needed to complete the work in 42 days
Answers
Answered by
0
Step-by-step explanation:
6 persons in 35 days
let x person complete the work in 42 days,
then 6*35=42*x(inverse proportion)
therefore, on solving, we get x=5 person
Answered by
0
Answer:
7 people
Step-by-step explanation:
No. of person needed to complete 35 days work = 6
So , No. of person needed to complete 42 days work = 42/6
= 7 people are needed
Please mark me as brainliest .. Have a good day.