6 persons complete their work in 12 days if two more persons join them how many days are required to complete the work (ratio question )
Answers
Answered by
0
Answer:
if 6 persons in 12 days
Step-by-step explanation:
6+2=8 8 days
Answered by
0
Answer:
9 Days
Step-by-step explanation:
This is a case of inverse proportion, so xy has to be a constant.
6*12 = (2+6) * y
72 = 8y
y = 72/8 = 9 days
Hence, 8 persons will take 9 days to complete the work.