Math, asked by hruayee16, 1 year ago

6 persons completed a job in 18 days. how many days will 9 persons take to complete the same job?

Answers

Answered by Dikusneha
0

Plz mark it as brainlist

Answered by anitachumber8699
1

Answer:

27

Step-by-step explanation:

6x=18

x=18/6

x=3

therefore no of days to complete a work by 9 persons= 9x

                                                                                          =9(3)=27