Math, asked by prachi328, 1 year ago

6 persons finish a work in 4 days if they wkrk for 8 hours each day . How many hours each day should 6 person work if same work is to be done in 12 days ?​

Answers

Answered by sprao534
5

Number of hours to work =(6*4*8)/6*12=8/3 days

Answered by adityaanand26
3

Step-by-step explanation:

like me and mark me brainliest

Attachments:
Similar questions