6 persons take 10 days to dig a well. Number of days will 10 persons take to dig 3 wells
Answers
Given :-
- 6 persons take 10 days to dig a well.
To Find :-
- Number of days will 10 person take to dig 3 wells ?
Solution :-
~Here, we're given that 6 persons take 10 days to dig a well and we need to find the number of days 10 persons will take to dig 3 wells. Firstly we'll consider the data given to us and will find out how much well can be dug by a person in 1 day. Then, by considering the second case we can find the number of days 10 people will take to dig 3 wells.
_____________
Case - I
★ No. of days taken by 6 person = 10 days
★ No. of days taken by 1 person = 10 × 6 = 60 days
Case - II
★ No. of days needed by 10 persons
⇒ 60/10
= 6 days
10 persons can dig 3 wells in :
⇒ 6 × 3 days
= 18 days
____________
Hence,
- 10 people can dig 3 wells in 18 days.
☞ 6 persons take 10 days to dig a well. Number of days will 10 persons take to dig 3 Wells.
- 6 Persons take 10 days to dig a well.
- Number of days will 10 persons take to dig 3 wells
➜ Here, It's given that 6 persons take 10 days to dig a well and We have to work out number of days 10 persons will take to dig 3 wells. First, we will consider the data given to us and will work out how much well can be dug by a person in 1 day. Then, by considering the 2nd case, We can work out the number of days 10 persons will take to dig 3 wells.
Case - 1
➜ No. of days taken by 6 persons = 10 days
➜ No of days taken by 1 person = 10 × 6 = 60 days
Case - 2
➜ No. of days needed by 10 persons = 60/10 = 6 days.
➜ 10 persons can dig 3 wells in
= 6 × 3
= 18 days
Hence, 10 persons will take 18 days to dig 3 wells.