6 worker take 12 days to weed a field how many days would 12 worker take
Answers
Answered by
3
Answer:
6 days
Step-by-step explanation:
This is a case of of inverse variation.
6×12=12x
6×12/12=x
6=x
Therefore, 6 days
Answered by
1
x= 6,
therefore they will take 6 days to complete the work
Similar questions