6 workman can complete a job in 15 days.how many men should work ,if the job is to be completed in 10 days
Answers
Answered by
1
Answer:
4
Step-by-step explanation:
6:15
?:10
10 is 2/3 of 15
? should be 2/3 of 6
4 is 2/3 of 6, so ? = 4
Therefore, the number of men needed is 4