6 workman can complete a job in 15 days.how many men should work ,if the job is to be completed in 10 days
Answers
Answered by
4
Number of men needed to complete the job in 15 days= 6
Number of men needed to complete the job in 1 day= 15/6
Number of men needed to complete the job in 10 days= 15/6 x 10
= 6 and 10 get simplified to 3 and 5 so
15/3 x 5
=75/3
simplify the fraction
=25
Answered by
3
Answer:
9 workmen are required
Step-by-step explanation:
I hope it will help u