60. If 36 men do a work in 25 days,
then in how many days will 15
men do it?
(1) 30
(2) 60
(3) 45
(4) 15
Answers
Answered by
0
Answer:
60 days
Step-by-step explanation:
Given, 36 men can finish a piece of work in 25 days
=> The number of man-days = 36*25 = 900
Let x be the number of days taken by the 15 men to do the piece of work
=> The number of man-days = 15x
But the number of man-days remains constant.
=> 15x = 900
x = 900/15 = 60
=> 15 men take 60 days to complete the piece of work.
Hope, it will help you
Answered by
1
Answer:
hey
Step-by-step explanation:
Given, 36 men can finish a piece of work in 25 days
=> The number of man-days = 36*25 = 900
Let x be the number of days taken by the 15 men to do the piece of work
=> The number of man-days = 15x
answer is 60
But the number of man-days remains constant.
=> 15x = 900
x = 900/15 = 60