60 men can complete a piece of work in 40 days.60 men start the work but after every 5 days 5 people leave.in how many days will the work be completed?

Answers

Answered by shiv1112
1
52 days to complete the work
Answered by wifilethbridge
0

Answer:

The remaining work will be completed in 39 days

Step-by-step explanation:

60 men can complete a piece of work in 40 days

60 men 1 day work =\frac{1}{40}

60 men 5 days work =\frac{5}{40}=\frac{1}{8}

Remaining work =1-\frac{1}{8}=\frac{7}{8}

5 people leave now

Remaining people = 55

1 men 1 day work = \frac{1}{60 \times 40}

55 men 1 day work =  \frac{1}{60 \times 40} \times 55

                              = \frac{11}{480}

So, 55 men complete   \frac{11}{480} part of work in days = 1

55 men complete whole  work in days = \frac{1}{\frac{11}{480}}

55 men complete  \frac{7}{8} part of work in days:

= \frac{1}{\frac{11}{480}} \times \frac{7}{8}

= 38.18

Hence the remaining work will be completed in 39 days