60 men can complete a piece of work in 40 days.60 men start the work but after every 5 days 5 people leave.in how many days will the work be completed?
Answers
Answered by
1
52 days to complete the work
Answered by
0
Answer:
The remaining work will be completed in 39 days
Step-by-step explanation:
60 men can complete a piece of work in 40 days
60 men 1 day work =
60 men 5 days work =
Remaining work =
5 people leave now
Remaining people = 55
1 men 1 day work =
55 men 1 day work =
=
So, 55 men complete part of work in days = 1
55 men complete whole work in days =
55 men complete part of work in days:
=
=
Hence the remaining work will be completed in 39 days