60 people do some work in 20 days, if the same work is to be done with 40 men, how long will it take?
Answers
Answered by
0
Answer:
Step-by-step explanation:
Attachments:
vhardik166:
Where is the and??
Answered by
0
60people can do a work in 20days
one people fo this work in =60*20=120
40 man can complete this work in =120/40=3days
one people fo this work in =60*20=120
40 man can complete this work in =120/40=3days
D2 = 60*20÷ 40