Math, asked by Prerana912, 1 year ago

60men started the work to complete in 90days.They started the work, after 60days 3/4 of the work was completed.How many man should be discharged so that work will be completed on time?

Answers

Answered by Suhrithnpksistla
1
he should discharge 20men