64 men can complete a work in 15 days then how in many days 24 men will be able to complete the same work
Answers
Answered by
0
In a 12 days 24 men will be able to complete the same work
Answered by
0
Answer:
40
Step-by-step explanation:
64 men = 15 days
24 men = 64*15/24
= 40 answer