64 men working 8 hours a day plan to complete a piece of work in 9 days. After 5 days, they were able to complete only 40% of the work. The number of hours they should work per day so as to complete the remaining work in 4 more days is
Answers
Answered by
5
Given,
64 men working 8 hours a day plan to complete a piece of work in 9 days. After 5 days, they were able to complete only 40% of the work.
To find,
The number of hours they should work per day so as to complete the remaining work in 4 more days is...
This question can be solved easily with help of formula....
M₁D₁H₁/W₁ = M₂D₂H₂/W₂
here, M₁ = M₂ = 64 men , D₁ = 5 days , D₂ = 4 days, H₁ = 8 hrs , H₂ = ?
W₁ = 40% , W₂ = 60%
so, 64 × 5 × 8/40 = 64 × 4 × H₂/60
⇒60 = 4H₂
⇒H₂ = 15 hours
therefore 15 hrs they should work per day so as to complete the remaining work in 4 more days.