65 A
Section 1 - B
1) If P and Q together can complete a job in 3 days while P
alone can do the same in 12 days, then how many days
would be required by Q to do the job alone?
A) 3 days
B) 4 days
C) 6 days
D) 12 days
Answers
SOLUTION
TO CHOOSE THE CORRECT OPTION
If P and Q together can complete a job in 3 days while P alone can do the same in 12 days, then how many days would be required by Q to do the job alone?
A) 3 days
B) 4 days
C) 6 days
D) 12 days
EVALUATION
Let P & Q can complete the job in x days and y days respectively
Then by the given condition
Also
Equation 1 - Equation 2 gives
Hence the number of days required by Q to do the job alone = 4 days
FINAL ANSWER
Hence the correct option is B) 4 days
━━━━━━━━━━━━━━━━
Learn more from Brainly :-
1. The average age of A and B is 12 years, B and C is 9 years and that of C and Dis 23 years. If the average age of A,...
https://brainly.in/question/33842744
2. The mean of 5 numbers is 39. If one number is excluded, their mean is 35, find the excluded number
https://brainly.in/question/33419522
Given : P and Q together can complete a job in 3 days while
P alone can do the same in 12 days,
To find : how many days would be required by Q to do the job alone
A) 3 days
B) 4 days
C) 6 days
D) 12 days
Solution:
P alone can do the same in 12 days,
=> P 1 day work = 1/12
P alone can do the same in Q days,
=> Q 1 day work = 1/Q
P and Q together can complete a job in 3 days
=> P and Q 1 day work = 1/3
1/12 + 1/Q = 1/3
=> 1/Q = 1/3 - 1/12
=> 1/Q = ( 4 - 1) / 12
=> 1/Q = 3/12
=> 1/Q = 1/4
=> Q = 4
Q alone can do the job in 4 Days
Learn More:
With p starting the work, working on alternate days, p and q can ...
brainly.in/question/12364364
with P starting the work, working on alternate days P and Q can ...
brainly.in/question/12303996
A+B alternatively can do work in 17days and B+A alternatively can ...
brainly.in/question/15296215