68. A boy do a work in 5 days working 7 h per
day. If he does 5 h per day, what would be
the number of days taken by him?
(4) 8
(3) 7
Answers
Answered by
2
Answer:
7 days
work content = 5 days x 7 hours = 35 day hours
Days = 35 day hours /5 hour = 7 days