6man 12woman kisi work ko 20 days ma complete karta hai to us work ko 8man 16woman kitna days ma complete karanga
Answers
Answered by
0
Answer:
40/3
Step-by-step explanation:
As the no of man and women are increasing by 1/3 hence the no of days should decrease by 1/3.
so now required days = 20-20/3
= (60-20)/3
= 40/3
Answered by
0
in 40 days they completed work