Hint. Ratio of work done by A and B = inverse ratio of ame taken by A and B.
11. A does 20% less work than B. IA can finish a piece of work in 7
Answers
Answered by
3
Here you are my friend
Solution:-
Ratio of percentage of work done by A and B = 80 : 100
Suppose B takes 'x' hours time to complete the work.
So,
⇒ 80 : 100 :: x : 15/2
⇒ 100x = 15/2*80
⇒ x = 600/100
⇒ x = 6 hours (Time taken by B)
So, the option (c) is correct.