9. A and B together complete a piece of work in T
days. If A alone completes the work in T + 3 days
and B alone completes the piece of work in T + 12
days, what is T?
(S.B.I.P.O., 2008)
11
Answers
Answered by
2
Answer:
6
Step-by-step explanation:
1/a+1/b=1/t
a=t+3
b=t+12
sloving we get t=6