Math, asked by rampzroy09, 22 days ago

7. A and B can do a piece of work in 18 days Band C in 24 days and A and C in 36 days. In
what time can they do it, all working together!


Answers

Answered by randeer20
0

(A+B+C)'s 1 day's work =

18

1

(A+B)'s 1 day's work =

24

1

(B+C)'s 1 day's work =

36

1

∴ (A+C)'s 1 day's work=(2×

18

1

)−(

24

1

+

36

1

)

⇒(

9

1

)−(

72

3+2

)

⇒(

9

1

72

5

)

⇒(

72

8−5

)

72

3

=

24

1

so A and C together will do the work in 24 days.

Answered by saideepKundu
0

The above picture is the answer

Step-by-step explanation:

PLEASE MARK MY ANSWERE AS BRAINLIEST ANSWER

Attachments:
Similar questions