7. A and B can do a piece of work in 72 days: B and C can do it in 120 days: A and C can do it in 90 days. In what time can A, B and C together finished the work?
Answers
Answered by
4
Answer:
60 days
According to question,
(A + B)’s one day’s work = \frac{1}{72}
(B + C)’s one day’s work = \frac{1}{120}
and (C + A)’s one day’s work = \frac{1}{90}
On adding all three,
2 (A + B + C)’s one day’s work = \frac{1}{72}+ \frac{1}{120}+ \frac{1}{90}
= \frac{5+3+4}{360} = \frac{1}{30}
∴ (A + B + C)’s one day’s work = \frac{1}{60}
∴ A, B and C together can finish the whole work in 60 days.
hence proved that A,B,C together finish work in 60 days
Answered by
1
60 days is ans
Step-by-step explanation:
(A+B) one days work = 1/72
(B+C) one days work =1/120
and
(C+A) one days work = 1/90
on adding all three ,
2 (A+B+C) one days work = 1/72 +1/120 + 1/90
=5+3+4/360= 1/60
so A B and C together finish the work in 60 days
Similar questions