7 A and B, working together can complete a
job in 3 hours. If A alone can do the job in
7 hours, in how much time can B alone
finish the job?
Answers
Answered by
1
Answer:
B alone can complete the work in 7/4 hours.
Step-by-step explanation:
A and B can complete the work in 3 hours and A alone can do the job in 7 hours.
We have to find that , in how much time can B alone finish the job.
Solution
A alone can do the work in 7 hours.
Then Let x be the time taken by B to complete the work.
Then,
1/x + 1/7 = 1/3
1/x = 1/3-1/7
Here , LCM of 3 and 7 is 21
∴ 1/x = 4/7
∵ 1/x = 4/7
x = 7/4 hours.