Math, asked by rahulraghuwnshi7, 3 months ago

7. A contractor employed 560 men to complete a project in 7 months. If he wishes to complete
the same project in 5 months. How many more men should be employ?

guys yeh question commercial method ka hai variation inversely hai..​

Answers

Answered by Dishan13082007
2

Answer:

Follow me first then I Will answer you

Answered by PhoenixAnish
1

Given:

A contractor employed 560 men's to complete project in 7 months .

To Find :

how many men's will be needed to complete same in 5 months .

Here it is inverse proportion

so, in inverse proportion

y = k / x ( k is constant )

here our y is no.of men's ( 560 )

while x is no.of months( 7 )

we have to find k ( constant ) here so, if

y = k / x

k = x × y

k = 7 × 560

k = 3920

K ( constant ) of this equation is 3920

now we have to find how many men's will be needed to complete project in 5 months

so,

y = k / x

y = 3920 / 5

y = 784

so, 784 men's will be needed to complete same project in 5 months.