Math, asked by rachitdumaru, 2 months ago

7. A piece of work can be finished in 5 days. If the work is done
for 2 days and left, what is the remaining part of the work
to be done.
ROVA​

Answers

Answered by sayantanmitra87
0

3/5

Step-by-step explanation:

2 days implies 2/5th work done and 1- (2/5) = 3/5th work left = 60% work is left