7. 'A' takes 12 days to complete a work. 'B' takes 15 days to complete the same work. If they work together, how many days they will take to complete the same work?
Answers
Answered by
1
Answer:
5 days
Step-by-step explanation:
Let x be the number of extra days
Work rate for A =W/12
Work rate for B = W/15
Now...
W/12 (3+x) +W/15x =W
3+x/12 + x/15 =1
therefore : x =5
Answered by
15
Answer:
▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂▂
A' takes 12 days to complete a work. 'B' takes 15 days to complete the same work. If they work together, how many days they will take to complete the same work?
▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬
Let us find the Work rate
Now, let us assume to be number of Extra Days.
(i) For A =
(ii) For B =
▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬▬
HOPES IT HELPS!:)
Similar questions