7. B is 200% efficient than A and 50% efficient than C, If all of them work together for 2 days to complete
the work, then in how many days A alone can complete the work?
Answers
Answered by
28
Gɪᴠᴇɴ :-
- B is 200% efficient than A.
- B 50% efficient than C.
- All of them work together for 2 days to complete
- the work.
Tᴏ Fɪɴᴅ :-
- in how many days A alone can complete the work ?
Sᴏʟᴜᴛɪᴏɴ :-
Given That, B is 200% efficient than A. .
So, we can conclude That :- B is Two Times Efficient than A.
or,
→ A : B = 1 : 2
Also, we have given That, B 50% efficient than C.
So,
→ B : C = 2 : 4
Hence,
→ A : B : C = 1 : 2 : 4 (Efficiency Ratio) .
Therefore,
→ (A + B + C) per day work = 4 + 2 + 1 = 7 units.
→ work complete in 2 Days = 7 * 2 = 14 units = Total work.
Now,
→ Whole work complete by A alone = (Total work) / (Efficiency of A) = 14/1 = 14 Days . (Ans.)
Hence, A alone can complete the work in 14 Days.