7. If 6 men and 8 boys can do a piece of
work in 10 days and 26 men and 48
boys can do the same in 2 days, the
time taken by 15 men and 20 boys to
do the same type of work will be
(a) 5 days
(b) 4 days
(c) 6 days
(d) 7 days
Answers
Answered by
0
Answer:
4 days
Step-by-step explanation:
Given that
6 men and 8 boys can do a piece of work in 10 days
26 men and 48 boys can do the same in 2 days
As the work done is equal,
10(6M + 8B) = 2(26M + 48B)
60M + 80B = 52M + 96B
=> M = 2B
=> B = M/2 ……(1)
Now Put (1) in 15M + 20B
=> 15M + 10M = 25M
Now, 6M + 8B in 10 days
=> (6M + 4M) 10 = 100M
Then D(25M) = 100M
=> D = 4 days.