Math, asked by ashwinbishnoi3, 5 months ago

- 7 men and 8 boys can do a piece of work in 2 days. 4 men and 12 boys can do29/56 of the same work in 1 day. In how many days will 1 man do this work?​

Answers

Answered by 236019tcs95
1

Answer:

1 man will do this work in 28 days.

Step by Step explanation:

hope it helps