7 men can complete a work in 12 days. They started the work and after 5 days two men left. In how many days will the work be completed by the remaining men?

Answers

Answered by kenzaniedrummond8
21

Seven men can complete the work in 12 days

TOTAL WORK =7×12= 84 parts

Up to 5 days, all of them worked together

So, work completed =5×7= 35 parts

Remaining work = 49 parts

As 2 men left, so there are 5 men to complete the remaining task.

So, TIME TAKEN = 9.8 days


Answered by qwcricket10
3

Given,

The number of men = 7.

The number of days 7men take = 12days.

The number of people left = 2.

To Find,

The number of remaining days to complete the work.

Solution,

Given that,

7 men finish the job in 12 days.

Let's take, the total work done = 12 * 7

84.

The work done by one man in a day =7unit

therefore,

Work done in first 5 days by 7men = 5*7

35unit.

After 5 days 2men left.

The work to be done in 7days = 84 - 35

49unit.

Therefore,

Let's find the total days to complete the job =

work/number of men

49/5

9.8days.

Hence, 9.8days are needed to complete the remaining work by 5men.