Math, asked by Yuvasarathiscientist, 11 months ago

7 men can complete a work in 52 days . In how many days will 13 men finish the same work ?​

Answers

Answered by devrathod26
0

answer to your question is 20

Answered by akhileshmishra11414
1

Answer:

Step-by-step explanation:

M1 = 7

D1 = 52 days

M2 = 13

D2 = ?

Step 2

Using formula

M1xD1 = M2 x D2

Then,

D2 = M1x D1 / M2

D2 = 7X52/13

D2 = 4 DAYS