7 men can complete a work in 52 days . In how many days will 13 men finish the same work ?
Answers
Answered by
0
answer to your question is 20
Answered by
1
Answer:
Step-by-step explanation:
M1 = 7
D1 = 52 days
M2 = 13
D2 = ?
Step 2
Using formula
M1xD1 = M2 x D2
Then,
D2 = M1x D1 / M2
D2 = 7X52/13
D2 = 4 DAYS