7 men can complete a work in 52 days. In how many days will 13 men complete the same work
Answers
Answered by
4
7 men complete the work in 52 days
1 man in 52/7 days
13 men in 52/7*13 = 96.5 days
1 man in 52/7 days
13 men in 52/7*13 = 96.5 days