7 men complete a work in 10 days .how many men complete the same work in 5 days?
Answers
Answered by
1
GIVEN :-
7 men complete a work in 10 days .
TO FIND :-
Number of men can complete the same work in 5 days.
SOLUTION :-
Now,
7 men completes a work in 10 days
1 men takes more time than 7 men so, a unique unitary method shall be used here. [INVERSLY PROPORTIONAL RULE]
7men = 10days
1 men = 70days
In five days, the no. of men required is -
70 × 1/5 = 14 men.
ALTER :-
Using Inversly Propertional rule
10 days taken by 7 men
5 days taken by ?
7/10 = 14/5
Here we can find that they are not equivalent but they follow rule of inversely proportion .